278 Little Lonsdale Street
Progess Update

Welcome to our latest news page. You'll find progess update for 278 Little Lonsdale Street Melbourne
Project Key Features
​
-
1 basement levels, consisting of residential and visitor parking, bike stores, storages, services, bin loading and storage
-
8 podium building levels, consisting of a ground level comprised of retail and residential concierge lobby and BOH areas, loading dock, and EOT facilities, bin rooms, storage, services, a retail tenancy, and hotel rooms
-
32 tower levels, for hotel rooms
-
Level 8 Hotel Lobby with courtyard
Milestone Dates:
-
Structure Completed (Building to level 32)
-
December 2025
-
-
Tower Crane Removal
-
February 2026
-
-
Lt Lonsdale and Zevenboom Works
-
April 2026
-
-
Overall Predicted Completion
-
July 2026
-

July 2025
Within the month of July 2025 Brady Hotel 278 is expected to complete concrete slabs up to Level 16 and the lift core up to level 22. Façade (windows) will progress install up to level 12 whilst services and finishes trades progress to level 7 internally by the end of July. Majority of CitiPower works (electrical authority) along little Lonsdale will be completed in this month minimising the interruption of road works and public interfacing along little Lonsdale street.